Basics and mounting

Mounting bus coupler

2.4 Mounting bus coupler
Proceeding
18
Requirements for UL compliance use
Use for power supply exclusively SELV/PELV power supplies.
The System SLIO must be installed and operated in a housing
according to IEC 61010-1 9.3.2 c).
There are locking lever at the top side of the bus coupler. For mounting and demounting
these locking lever are to be turned upwards until these engage. Place the bus coupler at
the mounting rail. The bus coupler is fixed to the mounting rail by pushing downward the
locking levers. The bus coupler is directly mounted at a mounting rail. Up to 64 modules
may be mounted. The electronic and power section supply are connected via the back-
plane bus. Please consider here that the sum current of the electronic power supply does
not exceed the maximum value of 3A. By means of the power module 007-1AB10 the
current of the electronic power supply may be expanded accordingly.
1.
Mount the mounting rail! Please consider that a clearance from the middle of the
mounting rail of at least 80mm above and 60mm below, respectively 80mm by
deployment of shield bus carriers, exist.
Clack
HB300 | IM | 053-1EC01 | en | 22-30
System SLIO