Control Box Installation
1. Decide the installation position of control box first, it is suggested to be installed near the gate and should
be protected from possible damage. Be aware of the motor cable length before deciding the installation position.
2. Remove the cover by unscrewing the four screws on the cover. See Figure A.
3. Use a screwdriver to puncture the holes beneath the bottom of the control box. See Figure B.
4. Secure it on the wall Figure C.
Figure A
Wiring Connection
24V A/C
Lit+ Lit- Lat+ Lat- M1+ M1- M2+ M2-
1
Flashing Light
PART B: Control System User Manual
Figure B
24V D/C
5V
S1
S2 GND Lmt1 Lmt2 GND Lmt3 Lmt4 GND
2
3
4
5
6
7
8
9 10 11 12 13 14 15 16 17 18
Electric Lock
Transformer
LED Display
LED2 Push button or Key selector
LED4 Photocell 1
LED3 Photocell 2
LED2
DKey SKey
GND
19 20 21 22 23 24 25 26
Push Button
Key Selector
Figure C
Wifi Device
UP
SET
DOWN
RF-LEARN
11
LED4 LED3
Ph1
PhVcc
GND
Ph2
PhVcc
Green Box
+5V INPUT
Photo Beams
TX
RX
9