Choosing the installation site

The installation site has to meet certain requirements. The following
questions should be clarified:
– Is the room height sufficient?
– Is there enough space available?
– Is the floor suitable for the weight of the CMM and the forklift?
– How strong are the floor vibrations at the installation site?
Disturbing floor vibrations may be caused, for example, by machines
in adjacent rooms or buildings.
– Does the installation site comply with all the ambient conditions re-
quired for perfect operation of the CMM?
– Is the installation site free from coarse dirt particles such as casting
sand and metal chips?
– Have the requirements for the compressed air supply been met?
– Are there problems with the power supply?
For more information, please refer to the »Installation site require-
ments«.
Carrying out vibration analysis
A vibration analysis must be carried out in any case. The result of the
analysis must be made available to ZEISS for planning purposes. An addi-
tional foundation may be necessary.
NOTE
ZEISS can carry out a vibration analysis for you. Please contact us if you
need our support.

Installation requirements

The following preparations have to be made prior to the installation of
the CMM by a ZEISS service engineer:
1 Ensure the flatness of the installation surface according to the instal-
lation instructions.
2 Installation of the power supply.
3 Installation of the compressed air supply.
4 Adapt the CMM to room temperature.