6)
Use #4 (60 ksi) reinforcing bar to tie the new pad to the existing
floor. Tie the bars together at intersections and use supports to hold
bars in the proper depth in the pad.
7)
After adhesive has cured, pour 4000 psi concrete up to level with
the existing floor plus any extra elevated pedestal desired 4-10" [102-
254].
Concrete must be done in one pour so that the entire pad cures as one
piece.
2.3.3.1
2.3.3.2
FLOOR:
8514-296-001 REV K page 10
NEW PAD TIED TO EXISTING FLOOR (LEVEL WITH FLOOR):
NEW RAISED CONCRETE PEDESTAL TIED TO EXISTING