Installation & Commissioning Checklist - Alpha ESS SMILE-B3-PLUS Owner's Manual

Hide thumbs Also See for SMILE-B3-PLUS:
Table of Contents

Advertisement

INSTALLATION & COMMISSIONING
2.
Installation & Commissioning Checklist (For Installers Only)
Following the SMILE B3 Plus installation, you must ensure the below checklist is
completed and a record of the same is shared with your system provider. It's also
recommended to retain records of the equipment installed.
No.
Items
1
System Provider (Contact details)
2
Primary Batteries
3
Secondary Batteries
4
Energy Meters
5
Total Battery Storage Capacity (kWh)
6
UN Number
7
Date of Installation & Commissioning
8
Firmware Versions
Inverter
BMS
9
Initial System Settings
Safety Regulation
Regional Application Standard
10
System Verification
Is the Battery Charging? (Y/N)
Is the Battery Discharging? (Y/N)
11
If Backup/UPS is Connected, does
the battery discharge towards
connected loads when Utility grid is
turned off? (Y/N)
12
DC Connections – Is there any high
resistance at the junction of the DC
cables & battery terminals? (Y/N)
Description
Model Number - SMILE-B3 PLUS (5.04
kWh)
S/N –
Model Number – SMILE-BAT-5P (5.04
kWh)
Number of batteries -
S/N –
S/N –
S/N –
S/N –
S/N –
Model Number – ACR10R / DTSU666
Number of Meters –
UN 3480
AS 4777.2
Australia A / Australia B / Australia C /
NZ
Grid Status - On
6
Grid Status - Off
N/A