Step 5: Set basic parameters, including PV capacity on the grid side, the type of me-
ters, safety regulations and regional application standard. Click "Submit" when the
settings are complete.
Note:
When the safety regulation is set as AS4777.2, the secondary sub-options can be se-
lected according to the region or local grid company (Please refer to Appendix 2).

Commissioning

6.1 Checking Before Power-On

Table 9-1 Installation checklist
No.
Check Item
Battery pack and in-
1
verter mounting
2
WiFi mounting
3
Cable layout
4
Cable tie
5
Grounding
Switch and breakers
6
status
___________________________________________________________________
Page 28 of 43
Acceptance Criteria
The battery pack and inverter are mounted cor-
rectly, securely, and reliably.
The WiFi module is mounted correctly, securely,
and reliably
Cables are routed properly as required by the
customer.
Cable ties are secured evenly and no burr exists.
The ground cable is connected correctly, se-
curely, and reliably.
All breakers connecting to or on the product are
OFF.