Check Before Power On; Eu Declaration Of Conformity - Goodwe ET Series Quick Installation Manual

Hybrid inverter
Hide thumbs Also See for ET Series:
Table of Contents

Advertisement

Available languages
  • EN

Available languages

  • ENGLISH, page 1
Inverter:
1. Terminals at the bottom of the inverter cannot bear much load. Otherwise, the terminals
will be damaged.
2. All labels and warning marks should be clear after the installation. Do not scrawl, damage,
or cover any label on the device.
3. Do not touch the running equipment to avoid being hurt as its temperature may exceed
60℃. Do not install the equipment at a place within children's reach.
4. Unauthorized dismantling or modification may damage the equipment, the damage is not
covered under the warranty.
5. Connect the BACKUP terminals before connecting the ON-GRID terminals. Do not start the
BACKUP function if the inverter is not connected to the battery.
6. Warning labels on the inverter are as follows.
High voltage hazard. Power
off the inverter first before
any operations.
Read through the guide
before any operations.
High-temperature hazard. Do
not touch the equipment to
avoid being burnt.
CE marking

Check Before Power On

No.
The inverter is firmly installed at a clean place where is well-ventilated and easy-to-
1
operate.
The PE cable, DC input cable, AC output cable, and communication cable are
2
connected correctly and securely.
3
Cable ties are routed properly and evenly, and no burrs.
4
Unused ports and terminals are sealed.
5
The voltage and frequency at the connection point meet the on-grid requirements.

EU Declaration of Conformity

The inverters sold in the European market meets the following directives and requirements:
• Electromagnetic compatibility Directive 2014/30/EU (EMC)
• Electrical Apparatus Low Voltage Directive 2014/35/EU (LVD)
• Radio Equipment Directive 2014/53/EU (RED)
• Restrictions of Hazardous Substances Directive 2011/65/EU and (EU) 2015/863 (RoHS)
• Waste Electrical and Electronic Equipment 2012/19/EU
• Registation, Evaluation, Authorisation and Restriction of Chemicals (EC)No 1907/2006 (REACH)
For more detailed declarations of conformity, visit https://en.goodwe.com.
Potential risks exist. Wear
proper PPE before any
operations.
Delayed discharge. Wait until
the components are totally
discharged after power off.
5min
Do not dispose of the inverter
as household waste.
Grounding point. Indicates
the position for connecting
the PE cable.