14. Re-connect the four signal harnesses to the AC relay.
TIP: Screws only need to be loosened to slip harnesses
on. Refer back to Figure 5 for the location of signal
harness connections. IMPORTANT! Loop the blue
and black signal harnesses around the clip once
(Figure 8) before connecting.
15. Re-connect the DC harnesses from the LVPS to the
Motherboard (PI & P2).
16. Re-connect J28 (black GPIO connector) to the Motherboard, if removed in STEP 6.
17. Replace the plastic AC relay cover.
18. Replace the EMI shield.
19. Replace the LVPS/Ballast cover.
20. Replace the top font cover.
To adjust LVPS voltage rails:
provided in the service kit when adjusting the LVPS voltage
rails on the CP2000-ZX LVPS.
by a qualified service technician.
1. Remove the LVPS/ballast side cover.
2. Adjust POT's to 3.366 +/-0.003v and 5.110v +/-0.003v.
Observe the CDP to see the adjustment value of the rails.
CP2000-ZX LVPS Upgrade Instruction Sheet
020-100461-01 Rev. 1 (11-2009)
Use the non-conductive plastic slot driver
LVPS rail adjustment must be performed
Figure 8
Figure 9