16
Installing the System in an Equipment
Rack
Before installing the Altos S700 Series in an equipment rack, it is
essential that the following guidelines are complied with, to ensure
the safe and efficient operation of the system. The Altos S700 Series
can be installed in open or closed equipment racks, with a front width
of 19", by observing the environmental, electrical, and mechanical
precautions described below.

Ambient Temperature

Installation of the rack system in a standard 19" cabinet may lead to a
differential between the room ambient temperature and the internal
ambient temperature of the rack environment. The operating
temperature of the Altos S700 Series is between 5
it is not recommended that the system be continuously run at these
extreme temperatures. Consideration should therefore be given to
ensure that the room ambient temperature is compatible with these
specifications.

Air Flow

To ensure that the internal heat build up is properly dissipated into the
room environment, air flow should in no way be restricted. It is
essential that no air vents are blocked, and that the system is a
minimum of one meter from a solid surface such as a wall or partition.
Air flow through the Altos S700 Series is from front to rear.

Mechanical Loading

Consideration should be given to the loading of any equipment racks.
To maintain a low centre of gravity (thus reducing the likelihood of
instability) racks should be loaded (where possible) from the bottom of
the equipment rack upwards. This is recommended to ensure personal
safety.
Caution: When installing or removing a rack mount enclosure,
remove all disk drives. It is recommended that you work with at
Chapter 2 Installation and Setup
o
o
C to 40
C. However,