Site Preparation Guide
Site Preparation Checklist
Electrical Installation Requirements
A dedicated outlet of 100-132, 200-240 VAC~15-7A 50/60 Hz has been installed.
The grounded electrical outlet is within 2 meters (80 inches) of the printer.
The grounded electrical outlet is able to accept either a Euro or US power cord plug.
If utilizing a LAN connection, the LAN connection is within 4 meters (14 feet) of the printer.
Environmental Requirements
The site's environmental temperature is between 59°F to 86°F (13°C to 30°C).
The site's environmental humidity is between 30% to 70%, non-condensing.
The site's altitude does not exceed 6561.68 feet (2000 m).
Required Installation Tasks
GrabCAD Print software has been downloaded and installed on the user's workstation PC.
The Welcome Kit and build trays have been removed from the oven chamber.
The orange clip securing the X belt in place has been removed.
The orange tie wrap securing the X motor in place has been removed.
Site Preparation Checklist