Completing the test

Continue to test another function or end the test by changing the TESTMODE setting to Disabled.
Restore connections and settings to the original values, if changed for testing purposes.
11.4.15

Phase preference logic PPL2PHIZ

Prepare the IED for verification of settings outlined in Section
11.4.15.1

Function revision history

Document
revision
A
B
C
D
E
F
G
H
11.4.15.2

Verifying the signals and settings

The Phase preference logic function PPL2PHIZ is tested with a three-phase testing equipment for
distance protections. PPL2PHIZ is tested in co-operation with the High speed distance protection
ZMFPDIS (21). The distance protection and the phase preference logic shall be set to values according
to the real set values to be used. The test is made by means of injection of voltage and current where the
amplitude of both current and voltage and the phase angle between the voltage and current can be
controlled.
During the test the following binary signals (outputs) shall be monitored:
Trip signal from distance protection
Trip signal from phase preference logic
1.
Connect the test set for injection of voltage and current.
2.
Inject voltages and currents corresponding to a phase-to-phase to ground fault within zone 1 of the
distance protection function. In the test one of the current inputs (one of the faulted phases) is
disconnected. The remaining current is the fault current out on the protected line. All combinations of
Transformer protection RET670
Commissioning manual
Fault type/Faulted phase current to the IED
A_BG/IA
A_BG/IB
B_CG/IB
No Trip
Trip
Trip
Trip
No Trip
No Trip
No Trip
Trip
No Trip
Product
History
revision
2.2.1
-
2.2.1
-
2.2.2
-
2.2.3
-
2.2.3
-
2.2.4
-
2.2.4
Setting ranges and setting descriptions have been updated in order to make the function
more user friendly. The added logic takes over if the relay detects the two faulty phases
within 20 ms and allows a larger margin of undervoltage to detect the faulty phases.
2.2.5
-
© 2017 - 2021 Hitachi Power Grids. All rights reserved
Testing functionality by secondary injection
B_CG/IC
C_CG/IA
C_AG/IC
No Trip
No Trip
Trip
Trip
No Trip
Trip
Trip
No Trip
Trip
"Preparing the IED to verify
Section 11
GUID-8BD66BC8-AAC3-41C4-B819-B159361688D2 v5
GUID-E1547542-1407-4488-AD99-2A7D063885A4 v2
settings".
GUID-F8B83D26-CCDC-4E1C-940A-F3B47A5AB4B0 v2
GUID-89399120-E87F-4380-8955-37BF1BAB34AF v1
163

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Relion 670 Series and is the answer not in the manual?

Questions and answers

This manual is also suitable for:

Ret670

Table of Contents