I N S T A L L A T I O N O F T H E S W I T C H G E A R A T S I T E
Fastening of the panels when using the reinforced
Fig. 2.3.2.3 a: View into
standard foundation frame
the cable compartment
of an example panel,
• To fasten the panels, use bars for each panel as
Fastening of the panel
a support, screws M 10 x 50 and washers (Fig.
on the reinforced
foundation frame
2.3.2.3 a). Refer to Fig. 2.3.2.3 b for the position
and number of fastening elements.
Fig. 2.3.2.3 b:
Fastening points of
the panels at the
corresponding
panel widths in case of
reinforced frames
Fig. 2.3.2.3 b
When a special foundation frame or raised false
floor is used
Fasten the panels in accordance with the
instruction documents supplied.
6 x Washer 10
6 x Cheese head screw M 10 x 50
3 x Bar
Fig. 2.3.2.3 a
6 x Washer 10
6 x Cheese head screw M 10 x 50
3 x Bar 390 mm
Section A-A, simplified
19