• Install the further panels in the manner described.
• Guide the control cables for the panel to panel
connections through the opening in the low
voltage compartment of the relevant adjacent
panel. Fit the control wiring plugs into the
corresponding connector sockets as shown in
the circuit diagram.
Fig. 2.3.2.6: View into
the cable termination
compartment:
installation of the
earthing bar
Fig. 2.3.2.6
Earthing link, as delivered
• Connect the earthing bars of the panels together
(Fig.2.3.2.6) by dismantling the earthing link
fitted at the works for transport, guiding it
through the opening to the adjacent panel and
tightening the screws with the specified torque.
Earthing link, mounted