ABB PrimeGear ZX0 Product Manual page 49

Gas-insulated medium voltage switchgear
Hide thumbs Also See for PrimeGear ZX0:
Table of Contents

Advertisement

O P E R A T I O N
Fig. 4.1.1 Earthing a
feeder and cancelling
the earthing
Fig. 4.1.2 Connecting
and disconnecting a
Feeder
feeder panel
disconnected
Fig. 4.1.3 Example
switchgear,
consisting of two
busbar sections, in
operation
Fig. 4.1.4 Opening
the circuit breakers
in the feeder panels
in the area of the
busbar section to be
earthed
Fig. 4.1.1
Fig. 4.1.3
Fig. 4.1.4
Earth feeder
Earthing
Feeder
prepared
earthed
Cancel feeder earthing
Connect feeder
Feeder
Connection
disconnected
prepared
Disconnect feeder
Fig. 4.1.2
49
Feeder
connected

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents