1. Installation Checkout
Use the Installation Checklist Table 2-3, to check the overall installation.
TASK
Preparation
Verify Electric Power Requirements.
Verify Gas Supply Requirements
Verify Exhaust Hood Requirements
Test supply water quality.
Check operating location clearances
Installation
Verify steamer is level.
Check drain line connection.
Check Exhaust Hood
Check electrical line connection.
Check water supply connection.
Test water supply lines.
Check Gas Supply Connection
Leak Test Gas Supply Connection
Check Burner Ignition Test
Perform Startup and checkout.
Notes on installation:
Table 2-3. Installation Check List
REFERENCE
Page No.
6 or 7
10
12
6 or 7
11
15
16
10
11
18
19
17
COMPLETED
8
8
9
8