11. Remove the cylinder rod from the holding fixture.
12. Position the cylinder barrel in a suitable holding fix-
ture.
EXTREME CARE SHOULD BE TAKEN WHEN INSTALLING THE
CYLINDER ROD, HEAD, AND PISTON. AVOID PULLING THE ROD
OFF-CENTER, WHICH COULD CAUSE DAMAGE TO THE PISTON
AND CYLINDER BARREL SURFACES.
13. With barrel clamped securely, and while adequately
supporting the rod, insert the piston end into the
barrel cylinder. Ensure that the piston loading o-ring
and seal ring are not damaged or dislodged.
3120826
Figure 2-14. Lift Cylinder
14. Continue pushing the rod into the barrel until the cyl-
inder head gland can be inserted into the barrel cyl-
inder.
15. If applicable, secure the cylinder head retainer using
a suitable chain wrench.
16. After the cylinder has been reassembled, the rod
should be pushed all the way in (fully retracted) prior
to the reinstallation of any holding valve or valves.
17. If applicable, install the cartridge-type holding valve
and fittings in the port block using new o-rings as
applicable. Refer to Table 2-2, Holding Valve Torque
Specifications.
– JLG Sizzor –
SECTION 2 - PROCEDURES
2-11

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

33rts40rts

Table of Contents