Test Operation; Check Work Prior To Turning Power Supply On; Turn Power On - Daikin RXSQ24TAVJU Service Manual

60 hz
Hide thumbs Also See for RXSQ24TAVJU:
Table of Contents

Advertisement

Test Operation

3. Test Operation
Follow the following procedure to conduct the initial test operation after installation.
3.1

Check Work Prior to Turning Power Supply ON

Check the below items.
Power wiring
Control transmission wiring
between units
Earth wire
Check on refrigerant piping /
insulation material
Check on amount of refrigerant
charge
3.2

Turn Power ON

Turn outdoor unit power ON.
Turn indoor unit power ON.
Carry out field setting on
outdoor PCB
131
Is the power supply appropriate?
Have you finished a ductwork to drain?
Have you detach transport fitting?
Is the wiring performed as specified?
Are the designated wires used?
Is the grounding work completed?
Use a 500 V Megger tester to measure the insulation.
Do not use a Megger tester for low voltage circuits.
Are the setscrews of wiring not loose?
Is the electrical component box covered with an insulation cover
completely?
Is pipe size proper? (The design pressure of this product is 4.0
MPa (580 psi).)
Are pipe insulation materials installed securely?
Liquid and gas pipes need to be insulated. (Otherwise causes
water leak.)
Are respective stop valves on liquid and gas line securely open?
Is refrigerant charged up to the specified amount?
If insufficient, charge the refrigerant from the service port of stop
valve on the liquid side with outdoor unit in stop mode after turning
power ON.
Has the amount of refrigerant charge been recorded on "Record
Chart of Additional Refrigerant Charge Amount"?
Be sure to turn the power ON 6 hours before starting operation to
protect compressors.
Close outside panels of the outdoor unit.
SiUS331708EA
Field Settings and Test Operation

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Rxsq36tavjuRxsq48tavjuRxsq60tavju

Table of Contents