CORNER INSTALLATION

1) Determine the exact position of the gas stove, making sure the
unit will be set at 45° to the walls and the corner clearance will not
be less then 1-inch. The vent pipe should be centred (if possible)
between two building members. This will avoid any extra framing.
2) Once the desired location is found, carefully measure up 23-
inches from the finished floor and make a mark. Next, measure 7-
inches plus the actual corner clearance of the appliance over from
the corner of the room and make a mark. (i.e. corner clearance of
1", measure 8"; corner clearance of 3", measure 10")
IMPORTANT: When locating this hole it should be noted that the
bottom of the vent terminal must be a MINIMUM of 12-inches
above grade, the top of the terminal must be a MINIMUM of 24-
inches below combustible material such as a deck or roof
overhang and the side of the terminal must be a MINIMUM of 12-
inches away from an adjacent wall. (See Figure 13)
3) Cut a 9-inch square or round hole through the exterior wall of the
building.
4) Position the wall thimble spacer (WTS) from the inside through
the 9-inch hole. (Figure 9). For walls less than 11-inches thick, the
thimble must be trimmed back flush with the exterior wall.
5) Attach the trim collar to the flanges of the wall thimble with the
screws provided.
6) Attach the coaxial 45° elbow (LB 45) to the unit. Slide the 5-inch
inner elbow pipe 1-inch over top of the collar and secure with three
sheet metal screws. Seal the joint with high temperature silicone.
Next, slide the outer elbow pipe over the smaller elbow and secure
to the pipe collar with three sheetmetal screws.
7) The coaxial starter pipe (SK 18) may have to be cut to length
depending on the wall thickness and/or corner clearance of the
stove. Measure the wall thickness from the finished trim collar
surface to the exterior mounting surface for the vent terminal. Add
3 3/4-inches plus corner clearance to the wall thickness. (i.e.
corner clearance of 1", add 4 3/4" , corner clearance of 3", add 6
3/4" to wall thickness)
Fig. # 10
8) Cut both pipes to this length.
9) Slide the inner 5-inch flue pipe over top of the crimped end of
elbow and attach with three sheet metal screws. Seal the joint with
high temperature silicone. Next, slide the 7-inch outer elbow pipe
over the 5-inch elbow fully and secure to the elbow with three
sheet metal screws. Assure that the vent pipe is level.
10) Slide the appliance into place making sure vent pipe is centred in
wall pass-through. When the unit is properly installed, the 7-inch
vent pipe will project 3/4-inch past the outside wall surface and the
5-inch inner pipe will extend 1-inch past that.
11) Install vent terminal according to section VENT TERMINAL
INSTALLATION
9