A ppe n di x B
Sensor3 Installation Checklist
CAUTION:
Job Number
Job Name
Rack
Check each box to confirm that the item has been
checked and is OK. Write NA if Not Applicable.
Beforehand
All material on site. Advise ETC of shortages
ASAP.
Electrical Contractor wiring OK
Confirm time and personnel for training.
DMX
Belden 9729 and ETC specified cables.
Daisy chain DMX.
Termination DIPs set correctly
Measure DMX termination from far end
Ethernet
Network star topology and using CAT5 or
better cable
Longest ethernet Run < 100m
Cable correctly terminated
Rack - Power Off
Top/bottom access plates in place and air gaps
sealed
Side plates in place and air gaps sealed
All air gaps, connections to conduit, and
trunking sealed
All bolts tightened to specification
Rack bolted to floor or wall
Neutral per load, no floating neutrals/earths in
system
All load wires and lugs tight
Fan spins freely
Phase-Earth high impedance (>500k ohms)
Phase-Phase high impedance (>500k ohms)
Load-Neutral impedance > 1 ohm: no "shorts"
Sensor3 Installation Checklist
This checklist is for use by authorised ETC trained personnel when energising
ETC Sensor3 racks. Do not attempt to energise a Sensor3 system unless you
are authorised and qualified to do so.
of
Rack clear of dust and debris
Dimmer modules: Chokes tight, hardware
tight, circuit breakers OK
Install dimmer modules
Install CEM3s
End User Training
Who received end-user training?
Contact ETC to return unused/defective goods
Detail any open items
37