Operating Guide | VACON® NXI Inverters FI9-FI14
Procedure
1. Switch off the DC supply voltage and wait until the inverter has stopped as advised in
Commissioning.
2. Connect the motor cable to the motor and to the motor terminals of the inverter.
3. Make sure that all Start/Stop switches are in Stop positions.
4. Turn the supply voltage switch ON.
5. Do again the Run test A or B, see
6. If the motor was not connected in the start-up test, connect the motor to the process.
7. Do again the Run test A or B, see

9.7 Motor Run Checklist

Context:
Do these checks before starting the motor.
Procedure
1. Check that the motor is mounted properly and ensure that the machine connected to the motor allows the motor to be started.
2. Set the maximum frequency reference (that is, the maximum speed of the motor) according to the motor and the device that is
connected to the motor.
3. Before reversing the motor, make sure it can be done safely.
4. Make sure that no power correction capacitors are connected to the motor cable.
5. Make sure that the motor terminals are not connected mains potential.
Danfoss A/S © 2019.11
9.5 RUN Test without
Load.
9.5 RUN Test without
Load.
Commissioning
9.1 Safety Checks before Starting the
AQ304441431479en-000101 / DPD00909| 89

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents