Commissioning; Overview: Commissioning; Precautions When Commissioning - Daikin VRV IV W+ Series Installer And User Reference Manual

Water-cooled system air conditioner
Hide thumbs Also See for VRV IV W+ Series:
Table of Contents

Advertisement

21
|

Commissioning

21 Commissioning
In this chapter

21.1 Overview: Commissioning

21.2 Precautions when commissioning

Installer and user reference guide
128
NOTICE
General commissioning checklist. Next to the commissioning instructions in this
chapter, a general commissioning checklist is also available on the Daikin Business
Portal (authentication required).
The general commissioning checklist is complementary to the instructions in this
chapter and can be used as a guideline and reporting template during the
commissioning and hand-over to the user.
21.1
Overview: Commissioning ...................................................................................................................................................... 128
21.2
Precautions when commissioning.......................................................................................................................................... 128
21.3
Checklist before commissioning............................................................................................................................................. 129
21.4
About the test run .................................................................................................................................................................. 130
21.5
To perform a test run ............................................................................................................................................................. 131
21.6
Correcting after abnormal completion of the test run.......................................................................................................... 132
21.7
Operating the unit .................................................................................................................................................................. 132
After installation and once the field settings are defined, the installer is obliged to
verify correct operation. Therefore a test run MUST be performed according to the
procedures described below.
This chapter describes what you have to do and know to commission the system
after it is configured.
Commissioning typically consists of the following stages:
1
Checking the "Checklist before commissioning".
2
Performing a test run.
3
If necessary, correcting errors after abnormal completion of the test run.
4
Operating the system.
DANGER: RISK OF ELECTROCUTION
DANGER: RISK OF BURNING/SCALDING
CAUTION
Do NOT perform the test operation while working on the indoor units.
When performing the test operation, NOT only the outdoor unit, but the connected
indoor unit will operate as well. Working on an indoor unit while performing a test
operation is dangerous.
RWEYQ8~14T9Y1B
VRV IV water-cooled system air conditioner
4P452191-1B – 2020.10