23 Commissioning

In this chapter

23.1 Precautions when commissioning

RXYSA4~6A7V/Y1B
VRV 5-S system air conditioner
4P600330-1A – 2020.07
NOTICE
General commissioning checklist. Next to the commissioning instructions in this
chapter, a general commissioning checklist is also available on the Daikin Business
Portal (authentication required).
The general commissioning checklist is complementary to the instructions in this
chapter and can be used as a guideline and reporting template during the
commissioning and hand-over to the user.
23.1
Precautions when commissioning.......................................................................................................................................... 135
23.2
Checklist before commissioning............................................................................................................................................. 136
23.3
Checklist during commissioning ............................................................................................................................................. 137
23.4
About the test run .................................................................................................................................................................. 137
23.5
To perform a test run (7-segments display) .......................................................................................................................... 137
23.6
Correcting after abnormal completion of the test run.......................................................................................................... 138
DANGER: RISK OF ELECTROCUTION
DANGER: RISK OF BURNING/SCALDING
CAUTION
Do NOT perform the test operation while working on the indoor units.
When performing the test operation, NOT only the outdoor unit, but the connected
indoor unit will operate as well. Working on an indoor unit while performing a test
operation is dangerous.
CAUTION
Do NOT insert fingers, rods or other objects into the air inlet or outlet. Do NOT
remove the fan guard. When the fan is rotating at high speed, it will cause injury.
INFORMATION
During the first running period of the unit, the required power may be higher than
stated on the nameplate of the unit. This phenomenon is caused by the compressor,
that needs a continuous run time of 50 hours before reaching smooth operation and
stable power consumption.
NOTICE
Be sure to turn on the power 6 hours before operation in order to have power
running to the crankcase heater and to protect the compressor.
During test operation, the outdoor unit and the indoor units will start up. Make
sure that the preparations of all indoor units are finished (field piping, electrical
wiring, air purge, ...). See installation manual of the indoor units for details.
23
Commissioning
|
Installer and user reference guide
135