IN
TWO-LINE RAIL CLOSURE
2.
2.1.
Install a platform angle post in the open corner pocket where the two-line rail will be attached
(FIG. 2.1). Secure in place as described in the 'HANDRAILS' section of the PATHWAY HD Code
Compliant Modular Access System Installation Manual.
2.2.
Insert 1-1/2" diameter 5/16"-18 threaded inserts in both ends of the 1-1/2" diameter top rail and
1-1/2" square 5/16"-18 threaded inserts in both ends of the midrail and barrier. Use a rubber
mallet or similar tool to fully seat as needed (FIG. 2.1).
The top rail, midrail, and barrier are specific to the platform size and should not require trimming.
2.3.
Connect the top rail, midrail, and barrier to the platform angle post using 5/16"-18 x 1" hex bolts
and 5/16" flat washers in the locations shown (FIG. 2.1).
Do not use a washer with the lowermost bolt.
Installation Supplement for PATHWAY® HD Steps
FIG. 2.1
Page 7 of 29