ofs.com
imagine a place®
Staks benching assembly
6.
Plug in one jumper cable between two power blocks.
7.
Jumper cable should pass through O-rings.
8.
Jumper cable end must be pushed in until it snaps into place.
9.
Plug in power in-feed into any receptacle block in the run.
10. Snap in duplex receptacles according to power requirements (usually determined
by an electrician).
11.
Place duplex receptacle inside receptacle block with clip pointing down and slide
sideways into terminal until receptacle clicks in place.
12.
On premium power blocks, replace end caps and face plates after duplex
receptacles are installed.
800.521.5381
Assembly instructions
O-ring
11
Need help?
Do you have a question about the Staks benching assembly and is the answer not in the manual?