System Shutdown, Startup, and Reset
Shutting Down the System in an Emergency
Thermo Scientific
Many maintenance procedures for the TSQ system require that the mass spectrometer be shut
down completely. In addition, you can place the TSQ mass spectrometer in standby mode if
the system is not to be used for 12 hours or more.
Contents
•
Shutting Down the System in an Emergency
•
Placing the System in Standby Condition
•
Shutting Down the System Completely
•
Starting Up the System after a Complete Shutdown
•
Resetting the Mass Spectrometer
•
Resetting the Data System
•
Turning Off Selected Mass Spectrometer Components
If you need to turn off the mass spectrometer in an emergency, use the following process.
CAUTION Place the Main Power circuit breaker switch, located on the power panel on the
right-side panel of the mass spectrometer, in the Off (O) position. See
Figure
36. This turns off all power to the mass spectrometer, including the vacuum
pumps. Although removing power abruptly will not harm any component within the
system, under normal conditions do not shut down the system with the main power
circuit breaker switch. For the recommended procedure, see
Completely"
on
page
52.
To turn off the LC, autosampler, and computer in an emergency, use the on/off switches on
the LC, autosampler, and computer, respectively.