ROUTE THE CABLES
1. Identify the VSN Visual Guidance cable (P/N 115-2020-018)
2. Disconnect the CM041 connection on the boom.
FIGURE 14. CM041 Connection
3. Tee in the 115-2020-018 cable into this connection by removing the factory connector nut and making the tee
connection on the front side of the center rack.
4. Route the VSN connector up and along the boom between the boom frame and front blue cover.
5. Plug the VSN connector into the VSN from below.
FIGURE 15. VSN Connection
6. Route the analog video cable down the lift arms, following hoses and ensuring plenty of slack in the cable near
the boom main frame.
7. Route the analog video cable under the cab to the preferred place to drill a hole in the floor of the cab.
NOTE:
Failure to properly route cabling will result in premature cable wear in high-crop conditions.
Installation: Route the Cables
INSTALLATION
15