• You will finish off the top of the roof with a ridge cap made from shingles.
BEGIN
1
Cut shingles into THREE pieces.
2"
(5 cm)
Weather Seal
2
Install first ridge cap flush to shingles at front, as shown.
3
Install second ridge cap 5" back, as shown.
SHINGLES - RIDGE CAP
Hint: Use cut-off pieces first.
2"
(5 cm)
2"
2"
(5 cm)
(5 cm)
Flush
5"
12,7 cm
FRONT OF
SHED
2"
(5 cm
2"
(5 cm)
Top of slot.
Note: • You will need about 20 - 22 cut pieces.
(1) Nail per side through weather seal.
FRONT OF
SHED
(1) Nail per side through weather seal.
Flush
56
Score shingle,
then snap-off angled cut.
20 to 22
Pieces