6
After shingles are installed over bend, nail down overlap using two roofing nails per tab.
7
Continue installing rows of shingles to the peak. At the peak make sure there is a maximum of 5" or less to the rain slot, as
shown below. If shingles overlap at ridge cut to peak with a utility knife.
Cut Off.
• If more than 5" to rain slot you must install another row of shingles.
8
Repeat steps 1 - 7 to shingle the opposite side of your roof. Trim shingles at ridge.
9
Once both sides are shingled you need to trim ends. Strike a chalk line 1" from edge.
10
Using your shingle hooked blade carefully cut shingles along chalk line.
FINISH
11
You have finished shingling your roof. Proceed to capping the ridge.
SHINGLES
continued...
(2) Nails per tab
5"
(12,7 cm) MAX.
Top of rain slot.
CUT
5"
(12,7 cm)
or less.
55

Advertisement

loading

This manual is also suitable for:

Value montana 8' x 9'Montana