Download Print this page

Handy Home Products VALUE Series Assembly Manual page 56

8-5/8" 244 x 296 cm

Advertisement

3
Install second row of shingles flush at top of first row's rain slots. Ensure 1" overhang or flush to drip edge at front,
stagger each row.
FRONT OF
SHED
1"
(2,5 cm)
Notch
Flush with rain slots.
4
Continue installing rows of
shingles by staggering at front.
FRONT OF
SHED
The shingle over the bend in the roof will be nailed down. You will need 3" to 4" of this shingle to extend downward over the
5
bend for nailing.
Look for either of the following:
• If the rain slot of the shingle installed over the bend is ABOVE the bend and 3" to 4" of it overhangs down over the bend,
continue shingling up to the peak. You have enough to nail shingle down over the bend.
FRONT OF
SHED
(7,6 cm to 10 cm )
• If the rain slot of the shingle installed over the bend is BELOW the bend, install the shingle over the bend and overlap the
rain slot to get the 3" to 4" overlap.
FRONT OF
SHED
(7,6 cm to 10 cm )
The shingle OVER the bend must be installed with a 3" to 4" overlap AND the rain slot above the bend.
SHINGLES
1"
(2,5 cm)
Notch
3" to 4"
3" to 4"
continued...
- OR -
54
BACK OF
SHED
Bend in roof
Flush with rain slots.
Bend in roof
Rain slot above bend.
Flush to rain slot.
Bend in roof
Rain slot above bend
Overlap rain slot

Advertisement

loading

This manual is also suitable for:

Value montana 8' x 9'Montana