Download Print this page
Teledyne ADX-500 Manual
Teledyne ADX-500 Manual

Teledyne ADX-500 Manual

Alignment of z-drive

Advertisement

Quick Links

Alignment of Z-drive for
ADX-500 and ASX-510

Advertisement

loading

Summary of Contents for Teledyne ADX-500

  • Page 1 Alignment of Z-drive for ADX-500 and ASX-510...
  • Page 2 If you have an old z-drive on the unit remove it off both the ADX and ASX-510. Remove the new Z-drive from the package and locate the end with the peek tubing coming out that has no mounting block attached to it as shown in the picture below. Pull the peek tubing until fully extended and cut to a 7”...
  • Page 3 Turn the rotor manually clockwise until the fitting is ready to be screwed in to the ADX. Screw the fitting into the ADX until tight. Also at this time attach the Z-drive to the asx-510 on the arm tube and also to the back by putting the peak through the slot around the rotor on the asx-510, you may have to loosen the clamp to get the peek tubing past it.
  • Page 4 If the slider doesn’t make it to the top or try’s to go to far then you will have to adjust the sensor. You will want the z-drive to go to top with @ 1/8” space between the top and the slider. To adjust the sensor turn the rotor as shown below and insert allen wrench (3/32) in hole in the top-center.
  • Page 5 Ensure power to instrument is off. Make sure that you have a sample probe in the Z-drive, and racks on the right and left of the tray. As shown in figure 1-1. There is no need for racks in the 2 middle sections of the tray.
  • Page 6 11. With the back of the autosampler off the edge of the table or cart. Locate the 4 cap screws located under the bottom of the autosampler. As shown in figure 1-3.(only one side is shown in picture) Figure 1-3 12.
  • Page 7 14. Turn on the autosampler. It should home x, y, and z-axis. 15. Now open the program that you downloaded off the website. It will open a tcomm debug window, then soon after will open the main window as shown in figure 1-5. Figure 1-5 16.
  • Page 8 22. Turn autosampler back on and when the sample probe gets to the next tube, do the same as you did on the first tube. Turn unit off align and tighten screw. As shown in figure 1-7. Figure 1-7 23. Turn unit back on and let unit run through all the 4 corners. 24.