6. Anchor the seed treater in position to prevent the machine from moving during
operation.
7. Inspect machine thoroughly for screws, bolts, fittings, etc. which may have come
loose during shipping.
8. The pump stand(s) should be placed on level ground close to the seed treater.
9. Attach the chemical tubing from the pump stand(s) to the static mixer on the seed
treater (below). Additional tubing may be added or removed to accommodate your
installation.
Static Mixer
Assembly
10. Setup the Automated Main Control panel at a place that is convenient to the
operator. This may include attaching the automated main control panel to the
seed treater, to the wall, or to the supplied control panel stand that will require
anchoring.
11. Connect the gray cable with light blue ends to one of PJCAN connections on the
bottoms of both the main control panel and the treater panel.
12. Connect the red cable to the PJESTOPA on the main control panel and then to the
PJESTOPB on the treater control panel. This cable must run from an A connection
to a B connection (never A to A or B to B). Connect the other red cable to the
PJESTOPA on the treater control panel and then to the PJESTOPB on the I /O
control panel. Connect the two red plugs into each of the remaining open
PJESTOP connections.
13. Connect the Ethernet cable from the main control panel to the I /O control panel.
14. Connect the cables from Pump Stand(s) to applicable port on the Main Control
Panel.