ABB CoreSense M10 Installation Manual page 78

Multi-gas monitoring system
Hide thumbs Also See for CoreSense M10:
Table of Contents

Advertisement

Figure 63 Instrument USB port
5 Turn on the instrument using the main power switch (see Figure 4). The update process will start
automatically and take a few minutes.
Messages will appear on the local screen during the update process. Also, the instrument may
reboot two or three times depending on the required updates for your system. The update process
is complete once a message appears indicating to remove the USB key and reboot.
6 When this message appears, remove the USB key.
7 Power off the system for a few seconds and power it on again.
You may be asked to calibrate the screen by touching the 4 crosses displayed on the screen.
Figure 64 Screen calibration
The system firmware is considered complete after this last step. Wait until the Dashboard page is
displayed for at least 4 minutes (after the reboot, the Dashboard page might be empty for the first
20 minutes).
78
Installation Guide