5) INSTALLATION

Super Bantam 225 AC it's a single-phase welding transformer, to be connected across two input phases.
The main cable is connected to the circuit breaker. The primary terminal is reconnectable for different input
voltages. The electrical diagram shows the different voltage connections procedures. Remove the cover
and change the primary connections as show at the electrical diagram.
Recommended cable areas and fuses ratings are listed below.
Connected the transformer across two input phases and ground connection according to regulations.
TABLE 5.1
Voltage (V)
220 - 60 Hz
110 - 60 Hz
Eletric Diagram
See page 25.

6) OPERATION

1) Connect the return cable to the work piece.
2) Turn the circuit switch to "1" there by connecting the transformer to the mains.
3) Make sure that the air inlets are not blocked.
4) Adjust desired welding current setting with the crank on the top the transformer.
Note 1:
When used in 220V (power supply) the maximum current is 225A.
Note 2:
When used in 110V (power suply) the maximum current is 110A.

7) MAINTENANCE AND SERVICE

The transformers require a minimum of maintenance. Under normal conditions, it is sufficient to blow the
transformer clean with dry compressed air with reduced pressure once a year. If used in a dusty and dirty
areas, it must be cleaned more often.
Spare parts for the transformers can be ordered from your local representative .

8) SPARE PARTS

See page 26 to 28.
16
Super Bantam 225 AC
Rating (kVA) for 40%
duty cycle
58
69
2
Cable (mm )
Fuse delay (A) or
Circuit-braker (A)
6
6
70
80