4.4 Mounting the boiler

Ensure the boiler and its controls are protected from
dripping or spraying water during normal operation.
The boiler should be installed in a location so that any
water leaking from the boiler or piping connection
or relief valve will not cause damage or the area
surrounding the unit or any lower floors in the
structure.
The boiler is delivered with a mounting template.
A hanging bracket situated at the rear of the casing
enables the boiler to be directly hung on the mounting
bracket.
CAUTION
Check the stability of the wall before mounting the
boiler.
Do not install the boiler on a non load bearing wall.
1. Position the mounting template to the wall with
masking tape.
CAUTION
Using a water level, check that the mounting
template is perfectly horizontal.
During mounting, cover up the vent to protect
the boiler and its connections from dust and
debris. Only remove this protection when the
vent is fitted.
The boiler must be installed such that no water
can get into the boiler casing and electrical parts
of the boiler.
2. Drill two Ø
the concrete.
3. Insert the
4. Attach the mounting bracket to the wall with the
provided
5. Hang the boiler on the mounting bracket.
6. Alternately, the hanging bracket can be affixed to a
½"/13 mm plywood sheet fixed to the wall studs or
a timber brace spanning the wall studs.
CAUTION
The boiler is delivered with a connection kit
accessory. Install this set before carrying out the
water and gas connections as described in the
installation examples.
MCA Pro 45/65/90/115
"/16 mm holes by 2"/50mm deep in
"/16 mmwall plugs.
"/16 mm bolts.