User Manual
7.4.3 Setting Feed-in Power
ON: no power could be fed into the
grid.
OFF: all system output power could
be fed into the grid.
Partial: partial of the output power could be fed into the grid.
When the existing system is disabled, the feed-in power ranges from 0
to the rated power of the existing system.
When the existing system is enabled, the feed-in power ranges from
(rated power of the existing system) to ([rated power of the hybrid inverter]
+ [rated power of the existing system]).
According to the local regulations in Germany, please set the feed-in
power to 70 % of the installation capacity.
For example, with a total maximum installation capacity of 4600 W
(SH4K6), the feed-in power should be set to 3220 W (i.e. 4600 * 70 %).
7.4.4 Setting System Time
The correct system time is very important. Wrong system time will directly affect
the data logging and power generation value. The clock is in 24-hour format.
DD, MM, and YY stand for day, month, and year
respectively.
hh, mm, and ss stand for hour, minute, and second
respectively.
7.4.5 Setting Backup Function
The backup function is disabled by
default.
If the backup function is enabled,
you should set the reserved capacity
for Li-ion batteries.
1/2
Zero-export
ON
OFF
Partial
Backup Setting
Disable
Enable
7 Commissioning
2/2
Partial
Feed-in Pwr[W]
05000
hh : mm : ss
Time
15 : 26 : 00
DD / MM / YY
Date
20 / 07 / 19
Backup Setting
Reserved Capacity
000 %
69