Testing by the customer

120/171
Siemens Building Technologies
HVAC Products
The contact material used with external signal sources (LP, RT, DHW flow switch, etc.)
should be gold-plated silver (also refer to «Technical data»).
Both the detector electrode and the ignition probe must be protected against electric
shock hazard.
Since the cable to the flame detector electrode must be well insulated against ground, it
must be protected against condensation, together with the detector electrode.
Input X1 for the unit's power supply must be connected to the power supply network as
follows:
X1-1 to L and X1-2 to N.
Connection of functional earth to X1-3 must be made in compliance with regulations !
If the boiler or burner manufacturer wants to conduct additional insulation or high-
voltage tests, they can only be made after prior approval by Siemens !
Basic Documentation LMU54... / LMU64...
9 Connection diagrams
CC1P7494en
07.11.2002

Advertisement

Table of Contents
loading

This manual is also suitable for:

Lmu64 series

Table of Contents