Initial Start-Up - HSM SP 5080 Operating Manual

Channel baling press
Hide thumbs Also See for SP 5080:
Table of Contents

Advertisement

4.3

Initial start-up

– Open the inspection door on the hopper and check that the press chamber is clear, and re-
move any spare parts or supplies delivered with the machine
– Insert the CEE Plug into the socket on site.
– Activate the emergency stop control by pushing the switch bar away from the machine.
– Unlock the emergency stop on the press. (optional).
– Switch on the main switch of the press and the shredder.
After a self-test by the control, the
Indicator: Manual mode – Initial position, appears
If the error number 1000 (= phase is absent) or 1010
(= counter-clockwise phase rotation) appear in the display -> call an electrician!
See also the "Malfunctions" section
Close the control cabinet, before continuing to commission the machine.
Set the desired user language
04/2013
Warning!!
Faults in electrical components and supply cables may only be attended
to by qualifi ed electricians or HSM service engineers.
2.990.999.120_en
SP 5080
35