Figure 3-35 Hole dimensions (unit: mm)
Step 2 Drill cabinet mounting holes in channel steel by using a hammer drill.
----End
Combining Power Cabinets and Bypass Cabinets
Step 1 The power cabinets and bypass cabinets are combined in the same way for ground installation
and channel steel installation.
----End
Securing the UPS
Step 1 Use common M12x45 bolts to secure the cabinets into the mounting holes in the channel steel
and tighten the bolts.
Step 2 Install the front, rear, left, and right anchor baffle plates.
----End