Final Check - Ingeteam INGECON SUN STORAGE 1Play Technical Manual

Hide thumbs Also See for INGECON SUN STORAGE 1Play:
Table of Contents

Advertisement

5 Final check

This chapter describes the instructions to check that all the connections and settings have been successfully
done.
1) Make sure that the CAN communication wire from the BYD battery to the inverter is connected.
2) Make sure that the battery circuit breaker is in ON position.
3) Make sure that the display´s screen of inverter is ON.
This can be done using the "Ingecon Sun Manager" software package or through the display:
Using the Display:
MAIN MENU > MONITORING > BATTERY MONIT.
Using Ingecon Sun Manager:
OnLine
If the error is showing, check again the instructions of this guide and otherwise contact with Ingeteam
Technical Service.
Technical Guide
Battery.Status doesn´t show "Error Communication with BMS"
11/04/2019
INGECON SUN STORAGE 1Play
STATUS doesn´t show "BMS ERROR"
7/8