Final Check; Configuration Of The Battery Settings - Ingeteam INGECON SUN STORAGE 1Play TL M Use And Settings

Hide thumbs Also See for INGECON SUN STORAGE 1Play TL M:
Table of Contents

Advertisement

Available languages

Available languages

Ingeteam

3 FINAL CHECK

This chapter describes the instructions to check that all the connections and settings have been
successfully done.
1) Verify that the CAN communication cable from the battery to the inverter is connected.
2) Verify that the inverter is on.
3) Access to the inverter and verify that there is no "Communication Error with BMS"
alarm.
3.1

Configuration of the battery settings

After the commissioning or the final check, it's recommended to configure the SOC levels in the
inverter.
Setting
SOC Max
SOC Min
SOC Recovery
Battery-Backup
If the operation mode is stand alone or the Battery-Backup function, it's activated. It's
recommended to configure the following settings.
Setting
SOC Recx
SOC Descx
The inverter allows managing the battery charge daily through the scheduling. By default, this
function is disactivated. For more detail, check the Installation and Operation Manual of the
INGECON SUN STORAGE 1PLAY TL M.
ABH2010IMC25_
Use and settings of the INGECON SUN STORAGE 1Play TL M working with eBick Ultra
175 of CEGASA
Operation mode: connected to grid
Description
Maximum state of charge for charging the batteries from the photovoltaic
energy (%).
Charge status under which battery discharge is not allowed when the grid
is available. SOC Recovery must be reached to resume the self
consumption with battery input.
Charge status above which the battery discharge resumes, once coming
from SOC Min.
This prevents excessive cycling, extending their work life.
In the event of a power outage, the energy required for critical loads is
supplied from the batteries and PV array. If this function is activated, the
SOC Recx and SOC Descx parameters need to be configured.
Operation mode: off grid
Description
Charge status above which the power supply to the critical loads is
restarted, once coming from SOC Descx (%)
Charge status below which the power supply to the critical loads when the
grid is not available and the Battery- Backup function is enabled (%)
15