Ingeteam

3 Final check

This chapter describes the instructions to check that all the connections and settings have been
successfully done.
1) Verify that the CAN communication cable from the battery to the inverter is connected.
2) Verify that the inverter is on.
3) Access to the inverter and verify that there is no "Communication Error with BMS"
alarm.