 8 Routine maintenance
If the checks listed below reveal conditions other than those foreseen,
they must be restored.
Operations
Frequency
Structures
Check the structure that the gate, plinth and building/fencing parts adjacent to
the automation are fastened to: absence of damage, cracks, fractures, failures.
Check the movement area of the gate: absence of obstacles, absence of objects/
deposits which reduce safety clearances.
Check the absence of hooking points or dangerous prongs.
Gate
Check the gate and its fastenings: integrity, no deformations or rust, etc.
Check the correct tightening of screws and bolts.
Check the concentricity between the upper hinge of the leaf and the lower rota-
tion fulcrum provided by the foundation box.
Check hinges and bearings: integrity, perfectly positioned and fastened in place,
no deformation, rust, etc.
Lubricate hinges and/or bearings if necessary.
Check the mechanical stops: fastening and solidity. Both sides must be checked,
simulating the impact that they could undergo during use.
Check the guide bracket of the leaf: integrity, absence of deformation and rust,
proper fastening, etc.
Check the absence of wear/collapsing which could jeopardise the condition that
all the weight of the leaf bears on the lower rotation fulcrum.
Check the anti-falling device: fastening and integrity.
General cleaning of the gate operating area.
Actuator
Check the integrity and correct fastening.
Check the sturdiness of the connections of the actuator to the leaf to avoid
uncontrolled movements of the leaf should it break.
Check the welding of the joint on the guide bracket.
Check reversibility and irreversibility.
Check that there is no oil leakage.
Top up the oil level, if necessary. Only use FAAC oil.
Bleed the oil, if necessary.
Clean the actuator and the foundation box
Check drainage efficiency.
Check the integrity of the actuator cables, of the cable glands and of the junc-
tion boxes.
Electronic equipment
Check the integrity of the electronic board enclosure.
Check the integrity of the power and connection cables and of the cable glands.
Check the integrity of the connectors and of the wiring.
Check that there are no signs of overheating, burns, etc. on electronic components. 12
Check the integrity and proper operation of the limit switches, if used.
Check the integrity of the earthing connections.
Check proper operation of the circuit breaker and residual current device.
Control devices
Check the integrity and proper operation of the installed devices and of the
remote controls.
Sensitive edges
Check: integrity, fastening and proper operation.
Deformable edges
Check: integrity and fastening.
Photocells
Check: integrity, fastening and proper operation.
Check the columns: integrity, fastening, no deformation, etc.
Flashing light
Check: integrity, fastening and proper operation.
Electric locks
Check: integrity, fastening and proper operation.
Clean the insertion seats.
S800 ENC
Access control
Check that the gate opens correctly only with authorised user recognition.
Complete automation
Check that the automation works properly, according to the programmed logic,
using the various control devices.
Check that the gate moves correctly, smoothly and regularly without any strange
12
noise.
Check its correct opening and closing speed and that it follows the intended
12
slowdowns.
12
Check proper operation of the manual release: when the release is activated, the
gate should only be able to be moved manually.
Check the presence of lock caps.
12
Ensure that the maximum manual moving force of the leaf is less than 220 N.
Check the proper operation of the safety edges for obstacle detection.
12
Check the proper operation of the encoder for obstacle detection.
Check the proper operation of each pair of photocells.
12
Check that there is no optical/luminous interference between the pairs of
12
photocells.
Check the limitation curve of the forces (standards EN 12453 and EN 12445). For
12
countries outside the EU, when there is no specific local standard, the force must
be less than 150 N static.
Check the presence, integrity and legibility of all the necessary signs: residual
12
risks, exclusive use, etc.
Check the presence, integrity and legibility of the CE marking of the gate and of
12
the DANGER AUTOMATIC MOVEMENT warning sign.
12
12
12
12
12
12
12
12
12
12
12
12
12
12
12
6
12
6
6
12
12
16
12
12
12
6
6
6
6
6
6
6
12
12
532116 - Rev.A