5. INSTALLATION

!
Installation must be carried out in compliance with Standards EN 12453
and EN 12445.
Close off the work site and prevent access/transit.

5.1 REQUIRED TOOLS

 6 Symbols: work equipment (type and size)
HEX WRENCH of the specified size (7, 8, 12)
7-8-12
CROSS-HEAD SCREWDRIVER of the specified size (6, 8...)
5
LEVEL
WELDER
INSTRUMENT with TORQUE ADJUSTMENT - if required for safety, a tool is
indicated with torque adjustment and the TIGHTENING TORQUE value. E.g.:
HEX WRENCH 6 set at 2.5 Nm
x.x Nm
2.5 Nm
6

5.2 REMOVE THE LEAF AND LOWER HINGE

If you automate an existing gate, the leaf must be dismantled and the
lower hinge removed before installing the actuator.
RISKS
PERSONAL PROTECTIVE EQUIPMENT
!
Anchor the leaf to the lifting device with a rope or a suitable chain.
After removing the leaf, place it on the ground or anchor it with a rope
or chain to prevent it from tipping over.
S800 ENC

5.3 PUT IN THE FOUNDATION BOX

RISKS
PERSONAL PROTECTIVE EQUIPMENT
!
The layout 21 of  3 provides approximate features of the founda-
tion for the leaf having maximum weight and length specified in the
Technical data. It is the responsibility of the installer to assess the
dimensions and materials of the foundation according to the features
of the ground, the gate and the installation environment. Perform
the structural calculation if necessary.
1. Perform excavations and set up separate pipes for the electrical cables
and drains (7 ).
2. Place the box with the hole aligned with the vertical axis of the upper
hinge (7).
3. Connect the pipes for the electrical cables and the drain.
4. Use a spirit level to ensure the box is horizontal.
5. Cement the box and wait for it to harden.
Ø MAX 35 mm