Carrying out emptying

4.1

Emptying / disposal process in general

Operating instructions must be displayed near the separator.
The disposal procedure must be carried out exactly according to the instructions.
Only allow approved disposal companies to carry empty out the grease separator.
The first disposal must be carried out within 2-3 weeks of initial operation.
Notes:
Subject to technical modifications!
Follow the accident prevention regulations!
During work on the open separator there must be NO SMOKING due to possible formation of biogas.
4.2

Emptying intervals:

According to DIN V 4040-2 and EN 1825, unless specified otherwise, sludge traps and separators must be
emptied, cleaned and refilled with fresh water every fourteen days, but at least monthly. In the case of DIN 4040
separators, the grease storage chamber must be emptied first and then the sludge trap; this prevents the sludge
tank from rising.
Attention: Correct function can only be guaranteed if the system content is disposed of in good time. For this
reason, a disposal contract should be concluded with a specialist company. If possible, disposal work should be
carried out outside business hours. When the separator tank is opened, odour pollution must be expected.
Workflow diagram for emptying cycle (Euro standard 1825)
A
B
C
D
A
Emptying period
B
Emptying vehicle is pumping off
C
hot water supply*
D
cold water supply
* recommended
2018/01
Carrying out emptying
13 / 18
Abb. [5]
010-916_SON_EN