8.2 Installation of P.T.O. Shaft (361 pump only)

WARNING: THE P.T.O. SHAFT ANGLE WILL CHANGE WHEN
Initial installation of the shaft is done as follows:
1. Attach the 3 point sprayer to tractor and set the sprayer in the
position with the shortest distance between the tractor and sprayer
pump P.T.O. shafts.
2. Stop the tractor engine and remove the ignition key.
3. If the P.T.O. shaft must be shortened, the shaft is pulled apart. Fit
the two shaft parts at tractor and sprayer pump and measure how
much it is necesary to shorten the shaft. Mark the protection guards.
Note: The shaft must always have a minimum overlap of 6" (150 mm)
46
RAISING AND LOWERING THE 3 POINT LINKAGE ARMS.
TO PREVENT EXCESSIVE LOADING AND
BINDING ON THE P.T.O. SHAFT, IT MAY BE ADVISABLE
TO LEAVE THE P.T.O. SHAFT DISCONNECTED UNTIL
THE PTO LENGTH ADJUSTMENTS ARE COMPLETED.
(Fig. 28).