6.5.13. Regeneration cycle step duration

Set the duration in minutes of each regeneration cycle.
Note
Setting a cycle step to 0 will cause the controller to skip that step during regeneration, but
keeps the following steps available.
Note
The different regeneration cycles are listed in sequence based on the regeneration flow
selected for the system.
Note
All cycles can be set from 0 to 199 minutes.
Note
The abbreviations used are listed on chapter 6.5.13.1.
6.5.13.1 Regeneration abbreviations
B1
First backwash
B2
Second backwash
BD
Brine draw
BF
Brine fill
BW
Backwash
LC
Last cycles
6.5.13.2 For pre-set regeneration cycles
AC Press
or
AD Press
to validate the selection and move to the next parameter.
Ref. MKT-IM-016 / C - 08.06.2018
to set the regeneration cycle step duration.
Installer Manual Fleck 5810 - SXT - Programming
RF
Refill
RR
Rapid rinse
SP
Service position
SR
Slow rinse
SV
Service position
65 / 106