Floor drain is always recommended to avoid flooding in case of overflow.

5.12. Brine line connection

The brine line from the tank connects to the valve. Make the connections and hand tighten. Be sure
that the brine line is secure and free from air leaks. Even a small leak may cause the brine line to drain
out, and the softener will not draw brine from the tank. This may also introduce air into the valve,
causing problems with the valve operation.
Most installations utilize a tank check valve.
Ref. MKT-IM-016 / C - 08.06.2018
Installer Manual Fleck 5810 - SXT - Installation
Overflow fitting
Drain tubing
Secure hose in place
Air gap
Drain