Phase Check - HELIX 9600 Installation, Operation And Maintenance Instructions

High voltage compressor
Table of Contents

Advertisement

Phase Check

Follow all high voltage safety precautions when performing this
procedure to prevent the possibility of electrical shock.
3-6
Part Number 8040437, Revision 104, 06/12/2007, ECO Number 18068
WARNING
1. Make sure power is applied to compressor circuit as described
in
Table
1-2.
NOTE: The circuit breaker will trip immediately during step 2 if the power
phase connections are not correct.
2. Turn the Compressor circuit breaker to the ON position. If the
circuit breaker trips, refer to step 3. If the circuit breaker does not
trip, refer to step 4.
3. If the circuit breaker trips, perform the following steps:
a. Turn the Compressor circuit breaker to the OFF position.
b. Disconnect the power cord from the power source.
c. Remove the circuit breaker terminal cover.
d. Reverse the wiring order of Compressor circuit breaker
terminals X and Y.
e. Torque the circuit breaker terminal screws to 12 in.-lbs.
f. Install the circuit breaker terminal cover.
g. Repeat steps 1- 2 of this procedure.
4. Install the rear panel.
5. Proceed with appropriate cryopump connections.
©2007 Helix Technology Corporation