Power Requirements; Grounding Requirements; Device Bay Thermal Requirements; Rack Warnings And Cautions - HPE Apollo z70 User Manual

Hide thumbs Also See for Apollo z70:
Table of Contents

Advertisement

Power requirements

Installation of this equipment must comply with local and regional electrical regulations governing the
installation of IT equipment by licensed electricians. This equipment is designed to operate in installations
covered by NFPA 70, 1999 Edition (National Electric Code) and NFPA-75, 1992 (code for Protection of
Electronic Computer/Data Processing Equipment). For electrical power ratings on options, refer to the product
rating label or the user documentation supplied with that option.
WARNING: To reduce the risk of personal injury, fire, or damage to the equipment, do not overload the
AC supply branch circuit that provides power to the rack. Consult the electrical authority having
jurisdiction over wiring and installation requirements of your facility.
CAUTION: Protect the server from power fluctuations and temporary interruptions with a regulating
UPS. This device protects the hardware from damage caused by power surges and voltage spikes and
keeps the server in operation during a power failure.

Grounding requirements

The building installation must provide a means of connection to protective earth.
The equipment must be connected to that means of connection.
A service person must check whether the socket-outlet from which the equipment is to be powered
provides a connection to the building protective earth. If the outlet does not provide a connection, the
service person must arrange for the installation of a protective earthing conductor from the separate
protective earthing terminal to the protective earth wire in the building.

Device bay thermal requirements

Operate the chassis only when a device or blank is installed in all device bays. Before powering up the
chassis, be sure to do the following:
Install a drive or drive blank into all drive bays.
Install a server or a blank into all server bays.
Install a power supply or power supply blank into all power supply bays.

Rack warnings and cautions

WARNING: When all components are removed, the system weighs 17.21 kg (37.94 lb). When all
components are installed, the system can weigh up to 22.65 kg (49.93 lb).
Before configuring your rack solution, be sure to check the rack manufacturer weight limits and
specifications. Failure to do so can result in physical injury or damage to the equipment and the facility.
Setup
19

Advertisement

Table of Contents
loading

Table of Contents