Installation Of The Pc In The Control Cabinet; Preparation Of The Control Cabinet; Earthing Measures - Beckhoff C6670-0010 Installation And Operating Instructions Manual

Control cabinet industrial server
Table of Contents

Advertisement

3.2 Installation of the PC in the control cabinet

The C6670-0010 Industrial Server is designed for mounting in control cabinets for machine and plant
engineering applications.
The ambient conditions specified for operation must be observed (see chapter

3.2.1 Preparation of the control cabinet

Four holes for the fixing bolts have to be provided in the control cabinet according to the dimensions of
the PC (see chapter
Assembly
Circulation of air
When the unit is installed in an enclosure, adequate space for ventilation and for
opening the PC must be provided.
Note
The clearance above and below the housing must be at least 5 cm in order to ensure
adequate ventilation of the PC.
Avoid extreme environmental conditions
Extreme environmental conditions should be avoided as far as possible. Protect the PC
from dust, moisture and heat.
Attention
The ventilation slots of the PC must not be covered.

3.2.2 Earthing measures

Earthing connections dissipate interference from external power supply cables, signal cables or cables to
peripheral equipment.
Establish a low-impedance connection from the earthing point on the PC housing to the central earthing
point on the control cabinet wall, in which the computer is being installed. The earthing connection is
located in the area of the connectors of the Industrial PC.